Select lowest number from Step 3-5.
Step 2 -- Absolute Input Voltage Constraint, Ns max abs = 15 units
Step 3 -- MPPT Voltage Constraint, Ns max mppt = 16 units
Step 4 -- System Voltage Constraint, Ns max pv = 26 units
The maximum number of PV modules that can be connected in series safety is 15 units.
Design And Sizing of Grid-Connected Photovoltaic Power System - SEDA Malaysia- 4th Published 2023
Example 4.6
SEDA GCPV Tutorial Design - Nov 2024
2. Sizing with string or central inverter - Question 3